LINCOLN MIDDLE SCHOOL MODERNIZATION BUILDING E PROJECT

X

HIGHLIGHTS: Work was performed while School was in session.
CLIENT: SMMUSD-Santa Monica-Malibu Unified School District
ARCHITECT: DLR Group & WW COT Widom Wein Cohen O’leary Terasawa, Architecture Engineering
DESCRIPTION: This project is to demo, abate the hazardous materials and renovate the existing building E as required. The renovation includes the science wet labs, classrooms and Type V-A Group E Sprinklers. The scope of work includes Construct New Walls and Ceiling, Repair then refinish the remaining wall, floor and ceiling surfaces, install a new utilities e.g. plumbing fixtures, gas furnace, ventilator, duct distribution system, lighting, communication and fire alarm system, a new fire sprinkler for the whole building and some site works around the parking lot.